Skip to content
contact@muskad.ma

022 MOSIP Connect

MOSIP Connect 2026 entrance arches

Fig. 01The dressed MOSIP Connect entrance arch in front of the building.

Two entrance arches and the marquee wrap for MOSIP Connect 2026 in Rabat, February 2026.

01The brief

Eleven days between the start of production on 27 January and installation on 7 February.

02What we did

The arches were built in the workshop, then lifted into place on site by the team in protective gear and dressed with their printed graphics. The marquee cover was printed on both sides.

04Images

Fig. 02In the workshop: the arch being built.
Fig. 03The team lifting the arch into place, in protective gear.
Fig. 04The arch lit at dusk, during finishing.

A similar project in mind?